Scheduling Handbook for Turnaround
I. Introduction
This handbook provides guidelines and best practices for external schedulers working on our turnaround events. The primary goal is to ensure a safe, efficient, and predictable turnaround by adhering to a dynamic and collaborative scheduling approach. Our methodology is built on a foundation of real-time data, proactive communication, and continuous optimization.
II. Scheduling Philosophy and Methodology
1. The Core Philosophy: From Static to Dynamic Scheduling
Traditional
scheduling relies on a static, "plan-and-execute" model. Our approach, inspired by Dynamic Scheduling Methodology(DSM), recognizes
that a turnaround is a complex and
ever-changing event. We shift from a
rigid schedule to a flexible, living document
that adapts to the realities on the
ground. This requires a mindset of continuous improvement and a willingness to
respond to new information as it
becomes available. Static scheduling is about measuring variance against the
plan. Dynamic scheduling (DSM) is about continuously recalculating and re-optimizing the
plan to drive.
2. The Three-Phases Scheduling Methodology
Phase One: Strategic
Planning & Schedule Foundations
The objective of this phase is to create a validated, resource-aware, and logic-driven baseline schedule that integrates all turnaround scope, highlights risks, and establishes a foundation for monitoring and control.
2.1. Establish Schedule
Foundations
The schedule is initiated by setting up a new project in the Primavera P6 database. The first step is to export approved work scope from SAP into P6 to populate the project with activities.
2.2. Define Major Milestones
All project
major milestones and key dates must
be included in the schedule. They must be logically linked to the network of
imported activities, ensuring they are actively driven by the schedule logic,
not just "floating dates." Examples include:
•
Project Start/Finish dates
•
Material delivery dates
•
Key interface dates
• Key pre- and post-commissioning dates
2.3. Establish Work Breakdown Structure
(WBS)
The WBS is the standard hierarchy in which work is organized. It serves as the backbone of the schedule, linking
scope to project controls reports. The required WBS levels are:
• Level 1: Site (e.g., PHOS)
•
Level 2: Plant (.g., Ammonia,
Beneficiation)
•
Level 3: Process
System
•
Level 4: Work Order
•
Level 5: Operations Tasks
2.4. Implement Schedule & Activity Coding
Activity codes
are used to filter, group, and sort information. They must be implemented early to capture all possible
reporting requirements and avoid
quality issues later.
Recommended codes include:
•
Plant name
•
Work order
•
Turnaround phases
•
Priority codes (useful for DSM operations)
2.5. Define
Schedule Calendars
The scheduler must create and assign the default project calendar, which defines normal working shifts, holidays, and exceptions. The baseline schedule must also accommodate weather events. This ensures that durations and resource plans reflect real working conditions. The guideline recommends specific shifts for different work groups, such as 7D x 12Hrs x 2Shift.
2.6. Develop a Project Resource Dictionary
The schedule
must be resource-loaded to align
with the project estimate. This requires two main steps:
1.
Developing a Resource
Dictionary of all possible resources
(labor, equipment, tools).
2. Creating a Table of Required
Resources in P6 and assigning them to activities.
Phase Two: Schedule Development & Quality Control
The goal of this phase is to build one unified, CPM-driven baseline schedule that logically links all activities across pre-work, execution, and close-out, ensuring float, dependencies, and sequence are visible and controllable.
3.1. Schedule Development Principles
Stakeholder Involvement: The scheduler facilitates the process, but key project personnel (e.g., project leads, engineering, operations) must be consulted to provide input on sequence, constructability, and resource usage.
Resource Loading: The schedule must be resource-loaded with man-hours and specific equipment, enabling reports at several levels of detail.
3.2. Schedule Logic Rules
The logic must be sound to support the CPM. Core rules include:
•
No open-ended activities (every activity has a predecessor and a successor)
•
Logic-driven dates rather than manual constraints
•
No negative float or negative lags
•
Retained logic must be used during updates
3.3. Schedule Quality Checks
Before approval,
the schedule must be checked
for:
•
Sound logic and a valid critical path
•
Minimal use of hard constraints and negative lags
• No excessive float (which could indicate
missing ties)
3.4. Basis of Schedule Document
The Basis of Schedule (BoS) document provides a narrative that defines the principles, assumptions, and specifications used in the schedule's development. It is the "user manual" for the plan, containing details on scope, constraints, risk mitigation strategies, and outstanding issues.
Phase Three:
Execution & Progress Monitoring
The objective of this phase is to execute the baseline plan to meet the established KPI targets using a dynamic, real-time control system.
4.1. Baseline & Current Schedule
Once approved, the schedule is signed off and saved as the Baseline Schedule, which is the frozen target for measuring performance. A copy is then used as the Current Schedule, a live, updated version maintained throughout the project.
4.2. Primavera Scheduling Options
The handbook specifies that schedulers must use a consistent set of standard Primavera settings to ensure uniformity and support dynamic calculation. This includes using retained logic and defining critical activities as those with float less than or equal to one shift.
4.3. Progress Monitoring & iPMS Integration
iPMS (Intelligence
Progress Monitoring System) transforms progress monitoring from a reactive exercise into a proactive control
system. Field progress, captured via tablets or mobile apps, is fed into iPMS
and then automatically pushed into Primavera. This enables:
•
Near-real-time visibility of the critical
path
•
Dynamic adjustment of the plan based on actual performance
• Automated reporting and analytics
4.4. Schedule Reporting
Reporting is
critical for communicating project status. The scheduler must provide a narrative analysis with each report, which
should include:
• Schedule Summary & Critical
Path
•
Summary of Progress & Slippage
Reports
• Resource Histograms & S-Curves {developed outside P6 with input from the schedule)
5. Post-Turnaround Scheduling Guidelines
This final phase closes the loop and ensures continuous improvement.
•
The as-built
schedule is frozen
to preserve a final
record of actual performance
•
A Variance Analysis
is conducted to compare the final schedule against the baseline
• Lessons Learned from the event are documented to improve future planning
• Historical iPMS data is used to calibrate productivity factors, durations, and
resource curves for the next turnaround.

Comments
Post a Comment